New Lathan Hall
The group would like to thank the MSF trustees, Subud Australia and Ken and Fatijah Clark for their support of this project and to give thanks to Almighty God for allowing this hall to come into being.
This new Latihan hall was opened on 17th Sept 2022 with a gathering of about 40 Subud members who enjoyed a celebratory lunch and an afternoon of latihan and kedjiwaan before attending Brasserie Cent Six in the evening. A wonderful restaurant owned by local members Lucy & Stephen Pulman. Here are some photos from the day and below that there are many project videos and pictures that will walk you though the birth of his new hall.
Progress Report No 7 (Sept 3rd 2022)
Progress Report No 6 (Aug 3rd 2022)
A lot has been happening in the last few weeks (see video below), as well as a lots to happen in the coming 6 weeks to be ready for the Opening Day on the 17th Sept. Next week the flooring will be laid, once's that's in the builder can start on the kitchen, then its the electricians for their final fit and air con. Then the plumber for his work including comissioning the septic system.
Progress Report No 5 (End of June 2022)
A big project milestone was completed on the 30th June when the septic system was delivered and installed. The video below gives further details. (In the start of video I give the update as June 2021, apologies for any confusion from that, I meant to say 2022.
Progress Report No 4 (Start of June 2022)
Recent activity has been the first fit out by the plumbers and first fit out of electrical wiring by the electricians and the trenching and laying out of electrical cabling to the water tank and to the site where the septic wastewater system will be located.
Progress Report No 3 (May 2022)
Progress Report No 2 (Feb 2022)
Progress Report No 1 (Dec 2021)
For further information about this project or the Sunshine Coast Subud Group contact the group chair Jonathan Evans at [email protected]